Axial Flux Coreless Coil Positioning Fixture

Record coil position, height and lead checks before potting. Export a traveler for review.

By CustomAxialFlux Engineering Editorial · Created · Reviewed

Coil Fixture Pre-Potting Inspector

Record coil checks before potting. Try two simulated held slots.

Loading interactive worksheet…

INCOMPLETE — hold for missing or invalid checks

0 checked pass · 0 flagged · 18 pending of 18 slots.

Slot inspection progress

Next: complete the required setup below, or load the illustrative example. A blank worksheet is also available.

Go to slot checks ↓ · Download blank worksheet

Required setup: all fields and datum confirmation. All slot observations are required for a complete record. Results update immediately; no server request. Uniform angular spacing and a one-sided height maximum only. PASS means the entered checks passed; finished stator clearance and production release are outside this tool.

Changing coil count clears slot observations. Mid-annulus chord is illustrative; use drawing coordinates for manufacture.

Isolation selections record pass/fail against your approved procedure. No test voltage, test duration or resistance threshold is supplied by this worksheet. An insulating nest alone is not a valid test electrode.

Pitch Step Nominal
--
Mid-annulus chord: --
Recorded Checks Pass
0 / 18
Flagged: 0
Max Measured Height
--
Limit: --
Illustrative Δdiameter
--
ΔT = 0°C (Fixture vs Cu)
Coil Pre-Potting Traveler: Slot Pitch Angle, Axial Height Z, Lead Exit & Isolation
SlotNominal (°)Measured Angle (°)Measured Height Z (mm)Lead Exit ChannelNest Isolation per PlanVerdict
Slot 1--°PENDING
Slot 2--°PENDING
Slot 3--°PENDING
Slot 4--°PENDING
Slot 5--°PENDING
Slot 6--°PENDING
Slot 7--°PENDING
Slot 8--°PENDING
Slot 9--°PENDING
Slot 10--°PENDING
Slot 11--°PENDING
Slot 12--°PENDING
Slot 13--°PENDING
Slot 14--°PENDING
Slot 15--°PENDING
Slot 16--°PENDING
Slot 17--°PENDING
Slot 18--°PENDING

Measured angles: 0 ≤ angle < 360° from Datum C; 359.98° is 0.02° from Slot 1 at zero. Positive heights only; no lower height limit is evaluated. Grey pending slots are not passing slots. Scroll the table horizontally on small screens.

Request DFM Review with These Fixture Datums

Share the current observation record, fixture drawing and unresolved checks for a DFM scope review. Include the approved electrical procedure and fixture revision.

Optional drawings & NDA

Files are delivered directly to our private engineering mailbox. No public download link is created. Review the drawing and NDA process.

For confidential drawings, complete the NDA with our team before uploading. An NDA request or template upload does not execute an agreement. Ask us by email if you need a different secure transfer method.

Email directly

If the form is unavailable, contact [email protected].

Four decisions before closing the mold

Decision summary: measured evidence before irreversible encapsulation
DecisionRequired evidenceWhen to hold
Locate from agreed datumsDrawing-defined axial plane, centering feature and angular zero; see datum concept and ASME scope [1].Fixture registration is unknown or differs from the drawing.
Separate pitch from heightUniform slot angle and measured peak Z; see explicit geometry method below.Any angle exceeds the entered tolerance, or peak Z exceeds the drawing maximum.
Check thermal fit in both directionsMaterial-grade coefficients and actual temperature; the tool is a free-expansion illustration [2].Binding, lost registration or unknown hot pocket clearance.
Keep electrical acceptance project-specificApproved procedure and traceable test record; instrument guidance depends on the equipment [3].No suitable electrode path, missing procedure or failed observation.

These are inspection planning decisions. Public sources support the method and boundaries; they do not demonstrate our fixture capability, a measured production tolerance or a qualified stator.

Coil fixture datum and pre-potting inspection drawing

Coil fixture datum and pre-potting inspection concept drawingC · Angular zero / indexB · Centering pilotA · Axial seating planeLead comb: no pinching
Scroll horizontally on small screens to read all labels. Concept only, not to scale. Twelve coils illustrate the datum scheme, independent of the worksheet slot count. Add drawing-specific pocket coordinates, tolerances, sections and inspection points before fabrication.

Use A to establish the axial measurement plane, B to center the annulus and C to identify Slot 1 and the positive angular direction. A round pilot leaves angular rotation free, so the index is a separate function. Avoid redundant rigid contacts that can deform a soft winding pack. This is a concept scheme; the designer must specify the actual datum features and restraint.

ASME Y14.43 addresses fixture and gage tolerance verification. Its public scope does not supply a coil-pocket flatness, draft angle or clamp load for this application. Read ASME’s scope [1] ↗

Drawing completion checklist — unknown dimensions stay unknown
Drawing featureAdd before fabricationInspection method to agree
A: axial seatSeat flatness, support pattern, surface finish and zero-height definition.Map the support plane with calibrated metrology.
B: pilot / centerDiameter, fit, axis relationship and allowance at process temperature.Check centering and hot-fit behavior.
C: angular indexIndex geometry, clockwise convention and winding map revision.Verify Slot 1 and absolute slot angles from the index.
Pocket and bridgeContact geometry, allowed compression, maximum Z and any lower limit.Measure peak height and distortion with the specified clamp condition.
Lead combLead bundle envelope, bend radius, insulation protection and seal design.Inspect the complete routing path with cover and seals installed.
Download datum concept drawing (.svg) ↓

Reproducible geometry and verdict logic

For N equally spaced slots, the exact nominal step is 360/N degrees and Slot i is at (i−1) × 360/N. The calculation keeps full precision before comparison. It displays rounded values only for reading. Angles use the shortest circular difference, so a reading just below 360° can be close to Slot 1 at zero.

The displayed reference chord is 2r × sin(π/N), where r=(OD+ID)/4 is the mid-annulus radius. This is a geometric illustration, not the winding’s actual reference pitch circle. For OD 280 mm, ID 180 mm and N=18, r=115 mm, step=20° and reference chord≈39.939 mm. Nonuniform, skewed or layered winding coordinates require a dedicated inspection plan.

Result states and the next action
StateMeaningNext action
INCOMPLETE / INVALIDMissing required setup or slot observations, or values outside the model range.Complete setup and measurements; use the blank worksheet if interactive entry is unavailable.
PITCH / HEIGHTAbsolute position or upper Z limit exceeded.Re-seat, remeasure and review the drawing limits; do not average away a high spot.
LEAD / ISOLATIONAt least one recorded observation failed.Correct routing or investigate under the approved electrical plan; the displayed badge shows one priority issue per row.
Recorded checks passEvery entered slot passes only the evaluated checks.Review full drawing, metrology uncertainty and process criteria before project sign-off.

Inputs accept positive geometry, 3–72 integer slots, angular tolerance below half a slot step and 0≤measured angle<360°. Temperature range −50 to 200°C is a model entry bound, not a material or process capability. The worksheet checks no lower height limit, flatness, coil width, gap between coils or 3D lead clearance.

Height screening supports a separate clearance budget

Coil height is one input to a separate assembled clearance budgetTop clearanceStator Z envelopeBottom clearanceCoils + insulation + encapsulation
Symbolic stack, no implied air gap dimension. Rotor runout, bearing motion, thermal distortion, resin flash and measurement uncertainty need separate allowances.

Do not force an oversize coil below the height limit by tightening the fixture. Resolve the winding or seating fault and use drawing-defined hard stops and controlled contact loads. Take peak Z readings from the agreed datum and clamping condition, rather than using an average coil thickness. The upper limit must come from the approved assembly stack. A passing unpotted coil height does not establish the finished resin surface, rotor running clearance or bearing motion allowance.

No force estimate follows from this height screen. Ansys distinguishes topology and winding conventions; its note on forces on stator teeth cannot establish a rotor bearing load from displacement of a nonmagnetic coil. A topology-specific coupled model is needed for magnetic force predictions. Ansys topology scope [4] ↗

Thermal mismatch: diameter growth is not pocket clearance

The illustration uses ΔD=D × (α_fixture−α_copper) × (T_preheat−T_ambient) × 10⁻⁶. A positive value means greater free fixture diameter growth; a negative value means copper grows more. Either sign can matter. Actual radial clearance requires the local pocket dimensions and restraint; for a simple radius, free radial growth is half the diameter change.

Illustrative constant coefficients in the tool — ppm/K, not certified grade data
Material modelCoefficientEvidence / limitation
6061 aluminum23.0Illustrative engineering assumption; replace with actual grade, temperature and supplier data.
P20 tool steel12.0Illustrative assumption; heat treatment and actual temperature range need confirmation.
Unfilled PEEK45.0Victrex 450G flow direction below 143°C [2]; not average isotropic expansion.
316 stainless steel16.0Illustrative assumption; actual stock and operating interval need confirmation.
Invar 361.2Illustrative assumption; lower expansion is not automatically a closer match to copper.
Copper reference16.5Illustrative free-copper coefficient; insulated winding packs may behave differently.

Example: a 280 mm aluminum reference diameter heated from 22°C to 85°C gives +0.115 mm differential diameter growth using these assumed coefficients. It does not prove a 0.115 mm loose pocket. Victrex reports different coefficients by direction and temperature; the tool blocks PEEK at 143°C and above. Datasheet, page 2 [2] ↗

Lead exits: inspect the closed routing path

Distinguish a dry positioning fixture from a sealed potting cavity. Springs, sliding locators or vacuum ports used for dry handling need separation from resin or an approved sealing design before exposure to liquid resin. Check each lead from coil body through comb, cover, seal and terminal transition. A visible free lead can still be pinched when a bridge or mold half closes. Use drawing-defined bend radius and contact geometry; this page supplies no universal wire-radius, seal-compression or spring-force value.

The worksheet stores a visual alignment observation. It cannot measure a bend radius, predict leak tightness or qualify a seal. For a failed observation, reroute the lead, inspect the enamel and recheck with the intended closure configuration.

Electrical observations require an approved test plan

Record the procedure revision and measurement-record ID before marking a slot’s isolation pass/fail. The approved plan must define voltage, duration, temperature correction, electrodes, connections, discharge and acceptance. Insulation resistance, dielectric withstand and inter-turn tests are different evaluations; one is not proof of all three.

An insulating nest alone supplies no conductive return path. A high resistance reading to such a support does not establish winding insulation integrity. Have qualified personnel use the approved configuration on a de-energized assembly. AEMC’s manual explains equipment-dependent voltage selection and test precautions; it does not establish a universal pre-potting limit. AEMC manual §§1.3 and 4.3.1 [3] ↗

Resistance or waveform imbalance may justify further investigation, but this tool cannot infer turn count, circulating current, torque ripple or heating from coil angular error alone. Winding connections, speed, induced voltage and branch impedance require separate analysis.

Fixture alternatives and practical cost tradeoffs

Compare fixture approaches before requesting a quote — no price or lead-time claim
ApproachPotential fitCost / mismatch risk and mitigation
Dedicated machined nestRepeatable registration for a stable geometry.Upfront tooling and revision cost; freeze datum and pocket drawing before machining.
Adjustable prototype fixtureGeometry is still changing.More setup and inspection labor; document each locked adjustment and recheck registration.
Combined mold and locating featuresApproved tooling can both locate and encapsulate.Limited measurement access and release risk; prove closure, access and removal on trials.
Printed sacrificial or prototype nestLow-volume fit investigation after material review.Creep, surface and temperature uncertainty; validate dimensions and process compatibility before use.

Hold points before resin delivery

Inspection and release responsibilitiesVerify A/B/CRecord slotsResolve holdsProject sign-offWorksheet output is an observation record, not release authorization.
Recheck the drawing revision and record changes after any re-seating, lead rerouting or fixture adjustment.
Risk, consequence and minimum recovery path
RiskConsequenceRecovery / alternative
Using sample values as drawing limitsFalse acceptance despite incomplete design data.Reset the example and obtain the approved tolerance stack.
Nonuniform winding forced into uniform slot modelIncorrect nominal angles and false verdicts.Use a drawing-specific coordinate sheet and optical/CMM inspection.
A single Z reading misses a tilted coilLocal high spot can escape screening.Map multiple prescribed points; do not treat this worksheet as a flatness inspection.
Rigid cold fit does not survive heatingBinding or loose registration at process temperature.Review grade-specific expansion, compliance and hot dimensional trials.
Flow load inferred from injection gauge pressureIncorrect pocket or clamp sizing.Determine actual pressure distribution and load path in a separate process review.
Incomplete traveler exported as releaseMissing or failed checks reach potting.Use the explicit hold status and require an independent project sign-off.

Three illustrative inspection scenarios

These are constructed worksheet examples, not customer cases, shop trials or measured production results.

Axial flux coreless coil positioning fixture worksheet run: 16 checked pass, two flagged slots and defect hold
Original software execution captured on 3 November 2026 using “Try 18-coil example”: OD/ID 280/180 mm, 18 slots, ±0.15° angle limit, 5.50 mm height maximum, aluminum, 22→85°C. Slot 5 is 5.62 mm and Slot 11 has a simulated lead misalignment. This verifies worksheet behavior only; floating contact chrome is hidden in this capture. Observations are simulated, with no hardware test, customer result or production qualification implied.

1. Two defects in an 18-coil example

Assume 280/180 mm envelope, 20° uniform spacing, ±0.15° angular tolerance and 5.50 mm maximum height. The loadable example has Slot 5 at 5.62 mm and Slot 11 with a misaligned lead. With all other simulated checks entered, the tool shows 16 passing slots, 2 flagged slots and a defect hold. Re-seat Slot 5 and correct Slot 11; no production outcome is implied.

2. Valid geometry, no measurements yet

After entering a valid setup for 24 coils, blank slot fields remain pending. A 15° nominal step is a reference position, not a measurement. Exporting produces an incomplete hold record. Measure every slot and record observations before requesting release.

3. PEEK model used outside its range

If a user selects PEEK and 160°C preheat, the constant-CTE illustration is withheld. Victrex 450G data change with temperature and direction [2]. Obtain the actual fixture grade’s data and evaluate the process separately; switching the dropdown to another material does not validate a PEEK fixture.

Fixture decisions: frequently asked questions

What does this coil positioning fixture worksheet decide?

It compares recorded uniform slot angles and maximum coil heights with user-entered limits, and records lead alignment and isolation observations. It does not release a stator for production.

What are Datums A, B and C?

In the concept sketch, A is the axial seating plane, B is a centering pilot and C is the angular index. These labels must be mapped to the approved part and fixture drawing; the sketch is not a toleranced manufacturing drawing.

Is coil pitch the same as coil height?

No. Angular pitch is the separation of coil reference directions around the axis; height is the axial Z envelope from Datum A. The worksheet checks absolute angular position and an upper height limit independently.

Can I use a nonuniform or skewed winding?

The angle model assumes N equally spaced reference positions, 360/N degrees apart. For staggered layers, skew or nonuniform layouts, use a drawing-specific coordinate inspection plan instead.

Is the displayed chord my coil pitch-circle dimension?

The chord uses the mid-annulus radius (OD+ID)/4 as a geometric illustration. The actual coil reference radius may differ. Use the drawing pitch circle for manufacturing coordinates.

How are angles near zero handled?

Enter angles from zero up to but excluding 360 degrees, measured from Datum C in the drawing direction. The comparison uses the shortest angular distance: 359.98 degrees is 0.02 degrees from zero.

What height tolerance should I enter?

Enter the approved maximum Z envelope. No default manufacturing tolerance is claimed. This is a one-sided screen: low coils, flatness, tilt and finished stator thickness require separate controls.

Does thermal differential equal radial pocket clearance?

No. The displayed value is an illustrative difference in free diameter growth using constant coefficients. Radial growth is half the diameter growth. Actual clearance depends on pocket geometry, restraint and temperature distribution.

Can I use the PEEK thermal model during a hot cure?

The worksheet stops the constant-CTE PEEK model at 143°C. Victrex 450G data distinguish direction and temperature regimes. Use grade-specific data and a separate process review outside this simplified model.

Which electrical test voltage and resistance threshold apply?

Use the project-approved procedure for the specific winding insulation system and test configuration. This page prescribes no voltage or resistance threshold. Record the test-plan and measurement-record references before selecting pass or fail.

Can an insulating nest prove winding isolation?

No. An insulating support alone does not establish a conductive measurement return. The approved test plan must define electrodes, connected components and accessible surfaces; a recorded pass is not independent verification.

Do the examples represent manufactured hardware?

No. They are explicitly illustrative input and decision examples. Example data remain marked as simulated after editing. Reset the worksheet to begin a project record.

Why can I export an incomplete or defective record?

A draft traveler is useful for resolving hold items. It includes pending and defect counts, per-slot verdicts and a hold status. Export is not permission to pot or release the assembly.

Does this page specify the resin or cure schedule?

No. This page owns coil positioning, drawing datums and pre-potting inspection. Resin selection, flow simulation, cure, exotherm and final stator qualification belong in the approved potting process.

Send a reviewable fixture brief

Provide the stator and fixture STEP/drawings, winding map, datum definitions, peak-height limits, lead and terminal interfaces, process temperatures, material grades, electrical test plan and held-slot traveler. Unknown dimensions, costs and process acceptance remain pending confirmation.

For the broader assembly and process scope, see coreless epoxy stator sub-assemblies. Confirm winding polarity separately with coil polarity testing.

Sources, dates and evidence limits

Public references checked on . Only public scope or datasheet content is cited. No claim is made that paid standards were reviewed in full. Geometry equations are reproducible definitions; uncited numerical coefficients are explicitly illustrative assumptions.

  1. [1] ASME Y14.43 — Gages and Fixtures ↗

    Public scope of fixture/gage tolerance verification; does not prescribe the example dimensions or coil tolerances.

  2. [2] VICTREX 450G technical datasheet (March 2026) ↗

    Page 2: flow-direction CLTE 45 ppm/K below 143°C and 120 ppm/K above; average CLTE differs. Supports model boundary, not fixture certification.

  3. [3] AEMC 6501/6503 megohmmeter user manual ↗

    Sections 1.3 and 4.3.1: de-energized testing and voltage selection by equipment and rating. Not a universal pre-potting acceptance specification.

  4. [4] Ansys Motor-CAD axial flux topologies ↗

    Topology and winding-current conventions. The stator-teeth force discussion does not validate a force estimate for an ironless coil fixture.